If the action has no tasks/ has task but weightings are not defined, then action progress will be as per the ‘Percent Complete’ set for that particular action.
However, if the action has tasks defined and weightings are given then action progress will be calculated as follows:
Task |
Complete |
Weightings |
Task1 |
65 |
25 |
Task2 |
50 |
75 |
Action ‘Percent Complete’ = [(65*25) + (50*75)] / 100
Note that, if an action has targets defined, then those targets will not be considered when calculating action progress.
Action Progress Traffic Light Indicator
Action progress traffic light will display the following indication based on the ‘Action Progress Threshold’ configured within the configuration area.
On Track - GREEN
Monitor - AMBER
Off Track - RED
Action Progress Traffic Light Indicator will display a blank traffic light in following instances
|